Server Upgrade from 5.1 to 5.2
|
Uyuni 5.1 must be stopped before the upgrade. |
|
Uyuni server hosts that are hardened for security may restrict execution of files from the For example:
In Uyuni updates, tools will be changed to make this workaround unnecessary. |
|
Before upgrading, verify that every root and intermediate CA certificate used by Uyuni marks If your installation uses an older self-signed CA generated by Uyuni, you might need to create a new CA and new server certificates, then deploy the new root CA to all clients. For the verification command, certificate replacement, and client root-CA deployment procedure, see administration:ssl-certs-imported.adoc#ssl-certs-verify-ca-basic-constraints, administration:ssl-certs-selfsigned.adoc#ssl-certs-selfsigned-create-replace, and administration:ssl-certs-imported.adoc#ssl-certs-import-deploy-root-ca. |
SSL certificates are needed at a later stage. If not using the self-signed generated CA and certificates, ensure you have the following before starting:
-
A certificate authority (CA) SSL public certificate. If you are using a CA chain, all intermediate CAs must also be available.
-
An SSL database private key.
-
An SSL database certificate.
All files must be in PEM format.
The hostname of the SSL server certificate must match the fully qualified hostname of the machine you deploy them on.
You can set the hostnames in the X509v3 Subject Alternative Name section of the certificate.
You can also list multiple hostnames if your environment requires it.
Supported Key types are RSA and EC (Elliptic Curve).
|
In the past, database SSL certificate required |
The database container needs only the externally facing fully qualified domain name.
The old certificates with db and reportdb SANs can be still used.
The same certificate can be used for both the main container and the database one.
In order to pass the new certificates to the upgrade command, use the --ssl-db-ca-root, --ssl-db-cert and --ssl-db-key parameters.
|
Upgrading to specific version
If you do not specify the tag parameter, it will default to upgrading to the most recent version. To upgrade to a specific version, provide the tag parameter with the desired image tag. |
During a migration the server SSL certificate and CA chain are copied from the source server, meaning that only the database certificates are required.
1. SL Micro 6.1 to SL Micro 6.2
This document provides the tested procedure to upgrade a SL Micro 6.1 host deployed with Uyuni 5.1 Server to SL Micro 6.2 and migrate to Uyuni 2026.06.
1.1. Prerequisites
-
Uyuni 5.1 is installed and running on SL Micro 6.1.
-
System is registered and has active subscriptions with SCC.
1.2. Distribution upgrade and server migration
Verify current product status.
SUSEConnect --status-textConfirm:
Base OS:
SL Micro 6.1Extension:
SUSE Multi-Linux Manager Server 5.1 ExtensionEnsure the system is updated.
transactional-update patch
If patches were applied, stop the server and then reboot the system before proceeding to migration:
mgradm stop rebootIf no updates were found, you can proceed directly to the migration step.
Start the migration.
transactional-update migration --auto-agree-with-licenses --gpg-auto-import-keysFollow the prompts and select the available migration to SUSE Linux Micro 6.2 and Uyuni Server Extension 2026.06.
Clean up the unused container images to free disk space:
podman image prune -a
In some upgrades, multiple
*.rpmnewand*.rpmsavefiles may be generated. The presence or number of these files does not indicate that manual action is required. In SUSE Multi-Linux Manager container environments, required configuration changes are applied automatically during the upgrade process. These files are created as a result of differences between packaged defaults and existing configuration files, and may also include internal or informational changes that are not intended to be merged. If manual action is required for a configuration change, it will be explicitly documented in the release notes or upgrade documentation.Do not treat these files as a post-upgrade checklist or merge them in bulk. Only review a file if you are actively troubleshooting a specific issue and understand the impact of the configuration it contains. If a change is required, it should be applied intentionally based on a known requirement, not by copying differences from these files. If you are unsure, leave the file unchanged.
Stop the server and then reboot to apply changes.
mgradm stop rebootPerform post-reboot checks.
Verify Uyuni extension and Uyuni version:
SUSEConnect --status-text mgradm --versionExpected output:
Extension:
SUSE Multi-Linux Manager Server 2026.06 ExtensionVersion:
mgradm version 5.2.0or higherUpgrade server containers.
Risk of Automated Version Downgrade and PTF Loss
Running the
mgradm upgrade podmancommand when no newer upgrade is available will cause the system to automatically revert to the base version. This process removes all currently applied Program Temporary Fixes (PTFs) without a confirmation prompt.To avoid unintended data or fix loss, verify upgrade availability before execution. Future releases will include a confirmation prompt to prevent this behavior.
mgradm start mgradm upgrade podmanFollow the prompts to pull and configure the new 5.2.x containers.
Verify PostgreSQL database version.
podman psExpected output:
server:5.2.0or higher
server-postgresql:5.2.0or higherClean up the unused container images to free disk space:
podman image prune -a
In some upgrades, multiple
*.rpmnewand*.rpmsavefiles may be generated. The presence or number of these files does not indicate that manual action is required. In SUSE Multi-Linux Manager container environments, required configuration changes are applied automatically during the upgrade process. These files are created as a result of differences between packaged defaults and existing configuration files, and may also include internal or informational changes that are not intended to be merged. If manual action is required for a configuration change, it will be explicitly documented in the release notes or upgrade documentation.Do not treat these files as a post-upgrade checklist or merge them in bulk. Only review a file if you are actively troubleshooting a specific issue and understand the impact of the configuration it contains. If a change is required, it should be applied intentionally based on a known requirement, not by copying differences from these files. If you are unsure, leave the file unchanged.
Verify running containers:
podman psYou should see all the expected server containers are up and running.
1.3. Migration complete
The server host system is now running SL Micro 6.2 with updated Uyuni 2026.06 Server packages.
If you have a Uyuni 5.1 proxy connected to this server, proceed to the Proxy Migration 5.1 > 5.2 guide to upgrade the proxy host.
Validate your setup before resuming production operations.
1.4. Database Backup Volume
Server migration or upgrade with mgradm migration or mgradm upgrade can create a volume with the database backup.
When the PostgreSQL database version is increased, the old database must be stored in a separate location before running the upgrade.
For this purpose mgradm dynamically creates the volume var-pgsql-backup.
When the migration or upgrade is done and the user has validated that the new system is working as expected, this volume can be removed safely.
2. SUSE Linux Enterprise Server 15 SP7
This document provides the procedure to upgrade a SUSE Linux Enterprise Server 15 SP7 host deployed with Uyuni 5.1 Server to Uyuni 2026.06.
2.1. Prerequisites
-
Uyuni 5.1 is installed and running on SUSE Linux Enterprise Server 15 SP7.
-
System is registered and has active subscriptions with SCC.
2.2. Server package update and migration
Verify current product status.
SUSEConnect --status-textConfirm:
Base OS:
SUSE Linux Enterprise Server 15 SP7Extension:
SUSE Multi-Linux Manager Server 5.1 ExtensionEnsure the system is updated.
zypper patchIf patches were applied, stop the server and then reboot before proceeding:
mgradm stop rebootPerform the migration to Uyuni 2026.06.
zypper migrationSelect to migrate to:
Uyuni Server Extension 2026.06Stop the server and reboot.
mgradm stop rebootPerform post-reboot checks.
Verify Uyuni extension:
SUSEConnect --status-textExpected output:
Extension:
SUSE Multi-Linux Manager Server 2026.06 ExtensionVerify Uyuni version.
mgradm --versionExpected output:
Version:
mgradm version 5.2.0or higherUpgrade server containers.
Risk of Automated Version Downgrade and PTF Loss
Running the
mgradm upgrade podmancommand when no newer upgrade is available will cause the system to automatically revert to the base version. This process removes all currently applied Program Temporary Fixes (PTFs) without a confirmation prompt.To avoid unintended data or fix loss, verify upgrade availability before execution. Future releases will include a confirmation prompt to prevent this behavior.
mgradm start mgradm upgrade podmanFollow the prompts to pull and configure the new 5.2.x containers.
Verify containers:
podman psExpected output:
server:5.2.0or higher
server-postgresql:5.2.0or higher
2.3. Migration complete
The server host system is now running SUSE Linux Enterprise Server 15 SP7 with updated Uyuni 2026.06 Server packages.
If you have a Uyuni 5.1 proxy connected to this server, proceed to the Proxy Migration 5.1 > 5.2 guide to upgrade the proxy host.
Validate your setup before resuming production operations.
2.4. Database Backup Volume
Server migration or upgrade with mgradm migration or mgradm upgrade can create a volume with the database backup.
When the PostgreSQL database version is increased, the old database must be stored in a separate location before running the upgrade.
For this purpose mgradm dynamically creates the volume var-pgsql-backup.
When the migration or upgrade is done and the user has validated that the new system is working as expected, this volume can be removed safely.